No flipping way...they don't even have the cable up yet. They have to hang the cable, splice it, adjust the sheaves, put on the chairs and gondola cabins, load test it, have ski patrol run evacuation protocols, and fix any punch list items before they can get it certified. At this point I'll be shocked if they can get it done by Dec 1st.Heard some news that the goal is to have American Eagle operating on Monday the 18th. Second hand information so don't take it as gospel and note the word "goal" in that sentence!
Copper is getting royally screwed over by Leitner Poma but I guess that's what happens when you decide to build two new lifts at the last second.